Over the past number of years, sections of Bay Bulls Road were upgraded with a 17.5 meter wide right of way. The scope of the current project involves the continued upgrading of Bay Bulls Road from Old Bay Bulls Road West (near Civic #100) to Long Beach Street.

The scope of work includes:

  • Installation of a new storm sewer system.
  • Storm laterals to each property.
  • Widening of the road, including new asphalt.
  • New sidewalks, curb and gutter on both sides of the road.
  • Re-alignment of Bay Bulls Rd and Old Bay Bulls Rd West intersection to provide a safer intersection for both drivers and pedestrians.

Occupational Health and Safety measures will be implemented based on the latest guidelines recommended for COVID-19.

Motorists and pedestrians are advised that Bay Bulls Rd will be restricted to local traffic only (residents, visitors and customers of businesses) from Old Bay Bulls Rd West (near Civic #100) to Long Beach Street in both directions beginning Tuesday, May 19th, 2020 at 7:00am until Friday, October 30, 2020 at 5:30pm.

Local traffic and emergency vehicles will have access with all other traffic detoured around the work site. Sidewalk and driveway access will be impacted. Traffic flow will be maintained by flagpersons and signage; slowdowns can be expected in the area. The City will make every effort to minimize disruptions and to maintain traffic flow.

We ask the public to obey and follow all posted signage in and near the construction zone.

This page is not intended to replace other information such as Public Advisories or Public Notices (e- updates), for day to day updates such as traffic or water interruptions, etc. check the City's website (External link). To keep informed of the City’s traffic advisories please sign up for e-updates at www.stjohns.ca.

Over the past number of years, sections of Bay Bulls Road were upgraded with a 17.5 meter wide right of way. The scope of the current project involves the continued upgrading of Bay Bulls Road from Old Bay Bulls Road West (near Civic #100) to Long Beach Street.

The scope of work includes:

  • Installation of a new storm sewer system.
  • Storm laterals to each property.
  • Widening of the road, including new asphalt.
  • New sidewalks, curb and gutter on both sides of the road.
  • Re-alignment of Bay Bulls Rd and Old Bay Bulls Rd West intersection to provide a safer intersection for both drivers and pedestrians.

Occupational Health and Safety measures will be implemented based on the latest guidelines recommended for COVID-19.

Motorists and pedestrians are advised that Bay Bulls Rd will be restricted to local traffic only (residents, visitors and customers of businesses) from Old Bay Bulls Rd West (near Civic #100) to Long Beach Street in both directions beginning Tuesday, May 19th, 2020 at 7:00am until Friday, October 30, 2020 at 5:30pm.

Local traffic and emergency vehicles will have access with all other traffic detoured around the work site. Sidewalk and driveway access will be impacted. Traffic flow will be maintained by flagpersons and signage; slowdowns can be expected in the area. The City will make every effort to minimize disruptions and to maintain traffic flow.

We ask the public to obey and follow all posted signage in and near the construction zone.

This page is not intended to replace other information such as Public Advisories or Public Notices (e- updates), for day to day updates such as traffic or water interruptions, etc. check the City's website (External link). To keep informed of the City’s traffic advisories please sign up for e-updates at www.stjohns.ca.

Consultation has concluded

Have a question about this project? Post it here and a staff person will get back to you as soon as possible. 

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Is Bay Bulls Road still under construction and is there still a detour there?

    Irene asked over 3 years ago

    Construction is complete for 2020 and the detour has been removed since the beginning of October.  The project is substantially complete, however there will be some minor work completed in May/June of 2021 which will not require a detour.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Will there be any placement of temporary speed bumps or something to slow traffic on Long Beach street, which is a residential street & now is being used as a high traffic main road

    Wayne C asked almost 4 years ago

    Temporary traffic calming (speed cushions, lights, etc) is not implemented during temporary detours created by construction projects. The detour via Long Beach is required for residents who live near that area of Kilbride. Concerns about speeding or other moving violations should be directed to the RNC as these are not within the City’s jurisdiction.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Will access to needs and Marie’s mini Mart be allowed?

    Laggan asked almost 4 years ago

    Yes, local traffic includes residents, business owners and visitors/customers to homes and businesses.  Please see this video from the City of St. John's titled "Local Traffic Only - What does it mean?" for more information: https://www.youtube.com/watch?v=SaAKMLJDJ_g 

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Is Bay Bulls Rd just west of cemetery included in this work?

    Pottlpa asked almost 4 years ago

    The work begins near Civic #100 Bay Bulls Rd to Civic #180 Bay Bulls Rd, as well as a portion of Old Bay Bulls Rd West near the intersection of Bay Bulls Rd.  Please refer to the Issued for Construction drawings in the Document Library for more information.